Arkansas
Mechanic's Lien
Deadlines & Filing Guide
Know your notice requirements, lien filing deadlines, and foreclosure deadlines before you lose your rights.
GET YOUR LIEN TOOLKIT
Required?
Subcontractors: 75 days from start + 10-day notice before filing
File by:
120 days after items furnished or work performed
Enforce by:
15 months from last day labor/materials furnished
Where found:
Ark. Code Ann. §§ 18-44-101 et seq.
File a lien in the office of the Circuit Clerk in the county where the property is located. Must include an itemized statement of account and a description of the property.
Contract
Signed
Work Begins
Signed
Preliminary
Notice
Subcontractors: 75 days from start + 10-day notice before filing
Last
Furnishing
File Lien
120 days after items furnished or work performed
Enforce Lien
15 months from last day labor/materials furnished