Connecticut

Mechanic's Lien

Deadlines & Filing Guide

Know your notice requirements, lien filing deadlines, and foreclosure deadlines before you lose your rights.

GET YOUR  LIEN TOOLKIT

preliminary notice

Required?

Not required

Lien Filing Deadline

File by:

90 days after last work performed; copy served on owner within 30 days after recording

Foreclosure Deadline

Enforce by:

1 year after recording lien

Statutory Authority

Where found:

Conn. Gen. Stat. §§ 49-33 et seq.

DEADLINE CALCULATOR

Enter your last day of work to calculate your deadlines.

PRELIMINARY NOTICE
Deadline
LIEN FILING
Deadline
FORECLOSURE
Deadline
Enter your last day of work to see your estimated deadlines.

Where and How to File:

Record a certificate of mechanic's lien in the town land records where the property is located. Must include property description, amount claimed, and name of person against whom the lien is filed. Serve a copy on the owner within 30 days of recording.

Important Notes:

Certificate of Mechanics Lien recorded in land records.

Quick Deadline Timeline

Contract
Signed

Work Begins
Signed

Preliminary
Notice

Not required

Last
Furnishing

File Lien

90 days after last work performed; copy served on owner within 30 days after recording

Enforce Lien

1 year after recording lien