Required?
Not required
File by:
45 days after completion (if Notice of Completion filed)
Enforce by:
3 months after lien recorded
Where found:
Haw. Rev. Stat. §§ 507-41 et seq.
File a notice of mechanic's and materialman's lien with the Bureau of Conveyances (or Land Court for registered land) in the circuit where the property is located. Must include property description and amount claimed.
Contract
Signed
Work Begins
Signed
Preliminary
Notice
Not required
Last
Furnishing
File Lien
45 days after completion (if Notice of Completion filed)
Enforce Lien
3 months after lien recorded