Idaho
Mechanic's Lien
Deadlines & Filing Guide
Know your notice requirements, lien filing deadlines, and foreclosure deadlines before you lose your rights.
GET YOUR LIEN TOOLKIT
Required?
Not required (residential projects require disclosure statement for GCs)
File by:
90 days after last furnishing
Enforce by:
6 months after filing lien claim
Where found:
Idaho Code §§ 45-501 et seq.
File a claim of lien with the County Recorder in the county where the property is located. Must include a statement of demand, property description, name of owner, and name of claimant.
Contract
Signed
Work Begins
Signed
Preliminary
Notice
Not required (residential projects require disclosure statement for GCs)
Last
Furnishing
File Lien
90 days after last furnishing
Enforce Lien
6 months after filing lien claim