Kansas

Mechanic's Lien

Deadlines & Filing Guide

Know your notice requirements, lien filing deadlines, and foreclosure deadlines before you lose your rights.

GET YOUR  LIEN TOOLKIT

preliminary notice

Required?

Subcontractors must provide warning letter; residential has different procedures

Lien Filing Deadline

File by:

Direct contract with owner: 4 months; Subcontractors: 3 months after last furnishing

Foreclosure Deadline

Enforce by:

1 year after filing lien statement (at least 90 days must pass)

Statutory Authority

Where found:

Kan. Stat. Ann. §§ 60-1101 et seq.

DEADLINE CALCULATOR

Enter your last day of work to calculate your deadlines.

PRELIMINARY NOTICE
Deadline
LIEN FILING
Deadline
FORECLOSURE
Deadline
Enter your last day of work to see your estimated deadlines.

Where and How to File:

File a lien statement with the Clerk of the District Court in the county where the property is located. Must include a verified statement of the amount due, property description, and name of owner.

Important Notes:

Quick Deadline Timeline

Contract
Signed

Work Begins
Signed

Preliminary
Notice

Subcontractors must provide warning letter; residential has different procedures

Last
Furnishing

File Lien

Direct contract with owner: 4 months; Subcontractors: 3 months after last furnishing

Enforce Lien

1 year after filing lien statement (at least 90 days must pass)