Mississippi

Mechanic's Lien

Deadlines & Filing Guide

Know your notice requirements, lien filing deadlines, and foreclosure deadlines before you lose your rights.

GET YOUR  LIEN TOOLKIT

preliminary notice

Required?

Not required for contractors/subs; sub-subs on commercial: within 30 days of beginning work; residential subs: 10-day pre-lien notice

Lien Filing Deadline

File by:

90 days after last furnishing

Foreclosure Deadline

Enforce by:

180 days after filing Claim of Lien (90 days if owner files Notice of Contest)

Statutory Authority

Where found:

Miss. Code Ann. §§ 85-7-131 et seq.

DEADLINE CALCULATOR

Enter your last day of work to calculate your deadlines.

PRELIMINARY NOTICE
Deadline
LIEN FILING
Deadline
FORECLOSURE
Deadline
Enter your last day of work to see your estimated deadlines.

Where and How to File:

File a claim of lien in the office of the Chancery Clerk in the county where the property is located. Must include an itemized account, property description, and name of owner.

Important Notes:

Quick Deadline Timeline

Contract
Signed

Work Begins
Signed

Preliminary
Notice

Not required for contractors/subs; sub-subs on commercial: within 30 days of beginning work; residential subs: 10-day pre-lien notice

Last
Furnishing

File Lien

90 days after last furnishing

Enforce Lien

180 days after filing Claim of Lien (90 days if owner files Notice of Contest)