Montana
Mechanic's Lien
Deadlines & Filing Guide
Know your notice requirements, lien filing deadlines, and foreclosure deadlines before you lose your rights.
GET YOUR LIEN TOOLKIT
Required?
Within 20 days of first furnishing (those not contracting directly with owner)
File by:
90 days after last furnishing
Enforce by:
2 years after filing lien
Where found:
Mont. Code Ann. §§ 71-3-521 et seq.
File a claim of lien with the County Clerk and Recorder in the county where the property is located. Must include property description, amount claimed, and name of owner.
Contract
Signed
Work Begins
Signed
Preliminary
Notice
Within 20 days of first furnishing (those not contracting directly with owner)
Last
Furnishing
File Lien
90 days after last furnishing
Enforce Lien
2 years after filing lien