Required?
Served no later than 10 days before recording lien
File by:
90 days after last furnishing
Enforce by:
3 years after filing lien
Where found:
N.D. Cent. Code §§ 35-27-01 et seq.
File a lien statement with the County Recorder in the county where the property is located. Must serve a copy on the owner no later than 10 days before recording.
Contract
Signed
Work Begins
Signed
Preliminary
Notice
Served no later than 10 days before recording lien
Last
Furnishing
File Lien
90 days after last furnishing
Enforce Lien
3 years after filing lien