Oklahoma
Mechanic's Lien
Deadlines & Filing Guide
Know your notice requirements, lien filing deadlines, and foreclosure deadlines before you lose your rights.
GET YOUR LIEN TOOLKIT
Required?
Required for those not contracting directly with owner; 75 days after furnishing (commercial/industrial)
File by:
4 months after last furnishing
Enforce by:
1 year after filing lien (at least 90 days must pass)
Where found:
Okla. Stat. tit. 42, §§ 141 et seq.
File a lien statement with the County Clerk in the county where the property is located. Must include property description, amount due, and name of owner.
Contract
Signed
Work Begins
Signed
Preliminary
Notice
Required for those not contracting directly with owner; 75 days after furnishing (commercial/industrial)
Last
Furnishing
File Lien
4 months after last furnishing
Enforce Lien
1 year after filing lien (at least 90 days must pass)