Oregon
Mechanic's Lien
Deadlines & Filing Guide
Know your notice requirements, lien filing deadlines, and foreclosure deadlines before you lose your rights.
GET YOUR LIEN TOOLKIT
Required?
Required for non-direct contractors (residential) and architects/engineers/suppliers (commercial); within 8 business days of first furnishing
File by:
Earlier of 75 days after last furnishing or 75 days after completion
Enforce by:
120 days after recording lien (extendable in 120-day periods up to 2 years)
Where found:
Or. Rev. Stat. §§ 87.001 et seq. (Construction Lien Law)
Record a claim of lien with the County Recording Office in the county where the property is located. Must include property description, amount claimed, and name of owner. Serve a copy on the owner.
Contract
Signed
Work Begins
Signed
Preliminary
Notice
Required for non-direct contractors (residential) and architects/engineers/suppliers (commercial); within 8 business days of first furnishing
Last
Furnishing
File Lien
Earlier of 75 days after last furnishing or 75 days after completion
Enforce Lien
120 days after recording lien (extendable in 120-day periods up to 2 years)