South Carolina

Mechanic's Lien

Deadlines & Filing Guide

Know your notice requirements, lien filing deadlines, and foreclosure deadlines before you lose your rights.

GET YOUR  LIEN TOOLKIT

preliminary notice

Required?

Not required for first-tier; Notice of Furnishing for remote claimants if Notice of Commencement filed

Lien Filing Deadline

File by:

Must file and serve no later than 90 days after last furnishing

Foreclosure Deadline

Enforce by:

6 months after last day of work

Statutory Authority

Where found:

S.C. Code Ann. §§ 29-5-10 et seq.

DEADLINE CALCULATOR

Enter your last day of work to calculate your deadlines.

PRELIMINARY NOTICE
Deadline
—
LIEN FILING
Deadline
—
FORECLOSURE
Deadline
—
Enter your last day of work to see your estimated deadlines.

Where and How to File:

File a statement and notice of mechanics lien (Certificate of Lien) with the Register of Deeds (or Clerk of Court) in the county where the property is located. Must serve a copy on the owner within specified time.

Important Notes:

Lis pendens required with foreclosure action

Quick Deadline Timeline

Contract
Signed

Work Begins
Signed

Preliminary
Notice

Not required for first-tier; Notice of Furnishing for remote claimants if Notice of Commencement filed

Last
Furnishing

File Lien

Must file and serve no later than 90 days after last furnishing

Enforce Lien

6 months after last day of work