South Carolina

Mechanic's Lien

Deadlines & Filing Guide

Know your notice requirements, lien filing deadlines, and foreclosure deadlines before you lose your rights.

GET YOUR  LIEN TOOLKIT

preliminary notice

Required?

Not required for first-tier; Notice of Furnishing for remote claimants if Notice of Commencement filed

Lien Filing Deadline

File by:

Must file and serve no later than 90 days after last furnishing

Foreclosure Deadline

Enforce by:

6 months after last day of work

Statutory Authority

Where found:

S.C. Code Ann. §§ 29-5-10 et seq.

DEADLINE CALCULATOR

Enter your last day of work to calculate your deadlines.

PRELIMINARY NOTICE
Deadline
LIEN FILING
Deadline
FORECLOSURE
Deadline
Enter your last day of work to see your estimated deadlines.

Where and How to File:

File a statement and notice of mechanics lien (Certificate of Lien) with the Register of Deeds (or Clerk of Court) in the county where the property is located. Must serve a copy on the owner within specified time.

Important Notes:

Lis pendens required with foreclosure action

Quick Deadline Timeline

Contract
Signed

Work Begins
Signed

Preliminary
Notice

Not required for first-tier; Notice of Furnishing for remote claimants if Notice of Commencement filed

Last
Furnishing

File Lien

Must file and serve no later than 90 days after last furnishing

Enforce Lien

6 months after last day of work