Tennessee

Mechanic's Lien

Deadlines & Filing Guide

Know your notice requirements, lien filing deadlines, and foreclosure deadlines before you lose your rights.

GET YOUR  LIEN TOOLKIT

preliminary notice

Required?

Prime: record contract prior to commencing; Subs: monthly notice within 90 days after last day of each nonpayment month

Lien Filing Deadline

File by:

Prime: 30 days after Notice of Completion; Subs: 90 days after last furnishing

Foreclosure Deadline

Enforce by:

Prime: 1 year after last furnishing; Subs: 90 days after filing lien (60 days upon demand)

Statutory Authority

Where found:

Tenn. Code Ann. §§ 66-11-101 et seq.

DEADLINE CALCULATOR

Enter your last day of work to calculate your deadlines.

PRELIMINARY NOTICE
Deadline
LIEN FILING
Deadline
FORECLOSURE
Deadline
Enter your last day of work to see your estimated deadlines.

Where and How to File:

File a notice of lien with the Register of Deeds in the county where the property is located. Prime contractors should record their contract before commencing work. Must include property description, amount due, and name of owner.

Important Notes:

Distinct requirements for prime contractors vs. subcontractors.

Quick Deadline Timeline

Contract
Signed

Work Begins
Signed

Preliminary
Notice

Prime: record contract prior to commencing; Subs: monthly notice within 90 days after last day of each nonpayment month

Last
Furnishing

File Lien

Prime: 30 days after Notice of Completion; Subs: 90 days after last furnishing

Enforce Lien

Prime: 1 year after last furnishing; Subs: 90 days after filing lien (60 days upon demand)