Required?
Notice of Intent within 90 days of completing work
File by:
90 days after project completion
Enforce by:
180 days after filing lien
Where found:
D.C. Code §§ 40-303.01 et seq.
File a notice of mechanic's lien with the Recorder of Deeds. Must include property description, amount due, and name of owner.
Contract
Signed
Work Begins
Signed
Preliminary
Notice
Notice of Intent within 90 days of completing work
Last
Furnishing
File Lien
90 days after project completion
Enforce Lien
180 days after filing lien