Required?
Subcontractors: Notice of Lien Rights within 60 days of first day of labor/materials
File by:
6 months after last furnishing
Enforce by:
2 years after filing claim of lien
Where found:
Wis. Stat. §§ 779.01 et seq.
File a claim of lien with the Clerk of the Circuit Court in the county where the property is located. Must include property description, amount claimed, and name of owner.