Wyoming
Mechanic's Lien
Deadlines & Filing Guide
Know your notice requirements, lien filing deadlines, and foreclosure deadlines before you lose your rights.
GET YOUR LIEN TOOLKIT
Required?
Not required
File by:
150 days from last furnishing or substantial completion; if Notice of Substantial Completion filed: contractors 150 days, materialmen 120 days
Enforce by:
180 days after filing lien statement
Where found:
Wyo. Stat. Ann. §§ 29-1-301 et seq.
File a lien statement with the County Clerk in the county where the property is located. Must include property description, amount due, and name of owner.
Contract
Signed
Work Begins
Signed
Preliminary
Notice
Not required
Last
Furnishing
File Lien
150 days from last furnishing or substantial completion; if Notice of Substantial Completion filed: contractors 150 days, materialmen 120 days
Enforce Lien
180 days after filing lien statement